This is a view of where the 1,204-foot bridge will go in the Quincy Bypass.
Bypass work on track

Progress on the Quincy Bypass, which will connect State Road 12 to U.S. Highway 90 near Ralph Strong Road and the Capital Regional Medical Center Gadsden Campus, is about 30 percent complete and work on the project is moving at a steady pace, according to Anthony Manos, project engineer.

 

“Much of the clearing is done about a third of the drainage is complete and about 30 percent of the earthwork has been done,” Manos said.